520K
Cubic Yds of Earthwork
12,000
Feet of Storm Sewer
12,000
Feet of Water Main
2,500
Feet of Sanitary Sewer

Gradex is working with ARCO Construction on a new Amazon Warehouse facility in Greenwood, IN called “Project Brutus”. The warehouse will be a total of 615,000 SFT under roof. In order to complete this project, Gradex will move 520,000 CYDs of earth, install 12,000 LFT of storm sewer, 12,000 LFT of water main, and 2,500 LFT of sanitary sewer main. This warehouse is being constructed under a very fast paced schedule, utilizing lime to dry the soils during the winter. Gradex is also committing up to 4 pipe crews at one time to install the underground utilities as quickly as possible. Gradex has the crews and resources available to expedite even the largest projects throughout the Midwest.

  • Category: Commercial / Warehouse